Key Considerations During Installation
Location Selection: Position the unit close to the dust source; minimize the length of suction ducting and the number of elbows to reduce airflow resistance.
Foundation Requirements: Use a C30-grade concrete foundation with a levelness deviation of no more than 3 mm/m; ensure a maintenance clearance equivalent to 1.5 times the equipment height.
Ductwork Configuration: Design the main duct with a constant diameter; limit branch diversion angles to 30°–45°; install high-temperature resistant silicone gaskets at flange connections; and tighten bolts diagonally in three stages.
Electrical Specifications: Maintain a 300 mm electromagnetic isolation distance between the control cabinet and the main unit; use shielded twisted-pair cables with ≥85% copper mesh coverage for pulse valve assemblies.
Precautions for Daily Operation
Startup Sequence: Start the dust discharge mechanism first, followed by the cleaning system, and finally the main fan; during shutdown, stop the dust-generating equipment first, allow the main fan to run for an additional 5–15 minutes, and then shut down the components in reverse order.
Parameter Monitoring: Stabilize the system differential pressure between 80 and 100 mm water column; keep the inlet gas temperature within the filter material's permissible operating range to prevent heat damage to the filter bags.
Cleaning Operations: Perform mechanical rapping/cleaning 3–4 times per shift; maintain pulse jet pressure between 0.4 and 0.6 MPa; and flexibly adjust the cleaning cycle based on dust characteristics.
Safety Procedures: Keep the electrical control box cover closed during operation; shut down the machine and cut off the power supply before adjusting parameters; and ensure personnel wear appropriate protective gear, such as dust masks and protective gloves.